Longer delays on Kessock Bridge expected tomorrow





Longer delays on Kessock Bridge tomorrow?
Longer delays on Kessock Bridge tomorrow?

Motorists are set to see further progress being made on the Kessock Bridge as carriageway surfacing works using a state-of-the-art material started yesterday.

The £13.2m improvement programme which enters into week 13 today, will see the second layer being put down tomorrow.

Following weeks of work, including preparation of the steel bridge deck and applying the new waterproofing system, over 1,500 tonnes of the specialist surfacing material gussasphalt will now be laid on the southbound carriageway of the Kessock Bridge. It is the first structure to use it in Scotland.

The special road surfacing material is very flexible and durable which means a longer service life, and is an advancement on the material originally laid on the bridge in 1982.

Calum Galloway, Bridges Manager for BEAR Scotland’s North West Unit, said: “A major benefit of this material on the bridge is that it can be laid in a continuous operation over the width of the carriageway without the need for joints and has increased durability. Other benefits include minimal future interventions for repairs, early skid resistance, and a smoother and more durable ride quality for the travelling public.”

The bridge, managed by BEAR Scotland, saw the refurbishment works to the southbound section of the 1052m-long structure start in February and has made good progress over the last 12 weeks of the improvement programme.

Calum Galloway added: “The machine used to lay the gussasphalt is quite unusual and we are aware that during the surfacing operations on Tuesday motorists may slow down to look. In order to avoid extended delays over the bridge, we urge road users to drive safely and to pay attention to the traffic conditions to help maintain a steady flow of traffic through the works.

“This is a complex job but the contractor Balfour Beatty Construction is working hard to ensure that works remain on schedule and that the bridge will be fully re-open as planned ahead of the peak tourist season.”

A reduced speed limit of 30mph and contraflow on the northbound carriageway will remain in place to keep both road users and workers safe. This could lead to delays, and motorists will be encouraged to avoid unnecessary travel into the city centre and to consider using public transport, car sharing, cycling or walking, where possible. Extra capacity on public transport, as well as additional parking at Ross County Stadium in Dingwall and Beauly train station, remains in place.

Motorists driving in and around Inverness can access up to the minute journey time information at www.trafficscotland.org. Further journey planning information is also available on Twitter and via the Travelline Scotland/Transport Scotland travel app.


Do you want to respond to this article? If so, click here to submit your thoughts and they may be published in print.



This site uses cookies. By continuing to browse the site you are agreeing to our use of cookies - Learn More